Damages & Financial Analysis
Documented amounts and assumption-based estimates are reported separately and never merged into a single headline number.
Documented
$582,700
Assumption-based
$258,540
Base scenario
Claimed, not adjudicated
| Category | Description | Value | Scenario | Calculation | Assumption | Status |
|---|---|---|---|---|---|---|
| Contractual damages | Unpaid Milestone 3 invoice | $412,000 | $412,000 | Invoice face value | Invoice is enforceable as issued | DocumentedUser Evidence |
| Interest | Contractual interest on late payment | $18,540 | $18,540 | 412,000 × 1.5% × 3 months | Rate applies from invoice due date | AssumptionAI Analysis |
| Documented expenses | Additional site staffing during delay | $96,400 | $96,400 | Sum of logged staffing entries | All entries relate to the delay | DocumentedUser Evidence |
| Lost revenue | Deferred downstream engagement | $240,000 | $240,000 | Estimated margin on deferred work | Engagement would have proceeded | AssumptionNeeds Verification |
| Fees | Professional fees incurred to date | $74,300 | $74,300 | Sum of invoiced fees | Recoverability subject to fee-shifting analysis | DocumentedNeeds Verification |